Owner Cockpit

Meridian Field Services, Inc.

Commercial mechanical & facilities services · Greenville, Charlotte, Augusta · 68 employees. Nine systems, one screen, refreshed before you wake up.

Mon 1 Sep 2026 · 6:41 AM
August closed · week 35
9 sources · 8 current · 1 needs attention
Cash on hand
$1.84M
+$212K vs 30 days ago
August revenue
$1.31M
+5.6% vs $1.24M plan
Gross margin
32.4%
−1.8 pts vs July
Signed backlog
$4.62M
14.2 weeks at current burn
AR past 60 days
$387K
12.1% of $3.20M book
Tech utilization
71.3%
−6.7 pts vs 78% target
Fleet 35 of 41 in service
2 collision 2 in shop 1 PM overdue 1 awaiting parts
18 vehicle-days lost in August · 2 open claims
Marketing $58.94 per lead
$12,260 Meta spend, August $1,430 per closed deal
208 of 306 leads came from paid

Revenue against plan

Trailing twelve months against the board plan. Seven of twelve months landed at or above.

Actual Plan
TTM revenue$13.00M
Variance to plan, TTM+$64K
Best / worst monthAug / Jan
Show the numbers
MonthActualPlanVariance

Needs you today

Ranked by dollars at risk, not by system.

CriticalPiedmont Regional is eating the month

MFS-2611 is tracking 5.9 pts under bid margin at 68% complete — $33.8K of the $55.8K total overrun across six active jobs sits on this one. Labor hours are 14% ahead of the cost curve.

Warning$291K of the past-60 AR is two customers

$387K past 60 days, 12.1% of the book. Both slow payers have open jobs still being invoiced — you are financing work you are still performing.

WatchThird week of soft utilization

71.3% against a 78% target while backlog holds at 14.2 weeks. The work exists; dispatch isn't reaching it. 1,684 available hours went unbilled in August.

Where the margin is

August gross margin by service line. Blended 32.4%.

Pipeline by stage

$7.85M open · $2.19M stage-weighted · 31% win rate over 90 days.

AR aging

$3.20M outstanding across 94 open invoices.

$387K past 60 days — the two darkest bands

Active jobs — bid margin vs. where it will land

Projected margin at completion is actual cost to date divided by percent complete, run against the contract value — the number the weekly job meeting is actually about.

Job Contract % comp. Budget cost
to date
Actual cost
to date
Variance Bid GM Proj. GM Status
Six active jobs $3,438,900 $1,807,500 $1,863,300 −$55,800 27.7% 25.1%